Resource and Code Assignment Validations Page of the Validity Check Wizard
Use this page to check if resource and code assignments in the project have invalid referenced data or undefined results.
Contents
Field | Description |
---|---|
Fix undefined results |
Select this check box to validate that the resource assignment uses a result that is defined in Resource Calculation. Cobra fixes undefined results. |
T-phase has invalid resource code |
Select this check box to verify that each time-phase record has a valid resource code. |
Resource assignments have budget, but no T-phase |
Select this option to determine resource assignments that have budget at complete (BAC) data but have no time phasing data. |
Resource assignments have calculation defined |
Select this check box to validate the following:
|
Key field code assignments still exist in code file |
Select this check box to validate whether the values assigned from the key field codes exist in the code file. This validates CA1 (Control Account 1), CA2 (Control Account 2), CA3 (Control Account 3), and work package key fields. |